In Schwedt, a power station to produce steam and electricity through the incineration of paper residue and refuse derived fuels is being built

The builder and future operator of the new incineration plant is Kraftwerk Schwedt GmbH & Co. KG (KSC), which is a joint venture by LEIPA and E.ON Energy from Waste AG (EEW).
EEW, as a 100-percent subsidiary of E.ON Energie AG, produces environmentally friendly electricity and process steam through the incineration of refuse derived fuels and waste. As the market leader in the market segment of waste incineration in Germany, EEW, together with local partners, develops, builds and operates incineration plants with a high technical and ecological standard.
At the end of the trial operation, the new plant should be completed by the beginning of 2010 and then take up regular operation.
Approximately 116,000 MWh of electricity and 600,000 MWh of process steam can then be produced each year through the incineration of a maximum of 220,000 tonnes of refuse derived fuels.
With the construction of the plant, approx. 50 new work places will be created in the incineration plant along with further work places in the service sector.

Project Task Distribution
Operator - LEIPA Georg Leinfelder GmbH
Management (repairs/maintenance, optimisation, invoicing) - KSC
Fuel procurement (preparation, logistics, purchasing, invoicing) - EEW
Plant supplier – Austrian Energy & Environment AG & Co KG (AE&E)

The Starting Position of the Building Procedure
Increasing energy costs caused LEIPA to revise its energy concept in 2004. At the same time, the arising residue of 220,000 tonnes per year from the paper production industry had to be disposed of in an environmentally-friendly manner. From this, a partnership between LEIPA and EEW developed.

The Objective
By reducing the annual energy costs by using refuse derived fuel and substituting the previous primary energy provider, natural gas, with process steam and electricity from the incineration plant, safe supply of the production site is guaranteed. At the same time, the incineration plant ensures long-term safe disposal of the residue arising from the production of paper on a waste paper basis and ensures the uninterrupted operation of the paper production industry. The energy from the residue is converted into electricity and process steam during incineration. This makes it possible to provide the basic load of the paper factory.

Fuels
- Residue from the paper production in Schwedt
- Refuse derived fuels (RDF)
RDF = prepared waste from commercial and household waste, without metal or toxins, low odour
  • Prepared to a high quality
  • With high fuel value
  • Hazardous substances pre-removed
  • From bio-mechanical treatment plants or mechanical treatment plants

Data compact
- 220,000 tonnes p.a. residue disposal from paper production
- 600,000 MWh p.a. steam production
- 116,000 MWh p.a. electricity production
- 136 MW thermal output

Schedule
October 2006    Submission of complete authorisation application to the State Environmental Office of Brandenburg (Landesumweltamt)
Mid 2007   Public display of application documents for four weeks
January 2008   Receipt of notice of approval for construction and operation
Beginning of 2008   Start of construction
End 2009   Beginning of cold start
February 2010   First fire with refuse derived fuels (RDF)
April 2010   Start of trial operation
June 2010   Start optimizing operation / Regular production operation

Building Phase
Please send your applications for the sections still to be tendered out to:

AE&E Inova GmbH
Dr. Wolfgang Hobbhahn
Bahnhofstraße 9
90402 Nürnberg
Tel. 0911 4627-212

Commissioning
To be able to subsequently operate the power station safely, the following employees will be sought after from spring 2009:

- Plant electrician
- Electrician / Crane driver
- Power plant operator
- Warehouse clerk
- Production manager
- Technical office manager
- Master in electrical engineering
- Master in mechanical engineering
- Authorities management clerk
- Commercial management clerk
- Shift supervisor
- Metal worker / Crane driver
- Supplier and disposer

Please send your applications for these positions to the following address before 28.02.2009:

E.ON Energy from Waste Premnitz GmbH
Human resource management
D. Herbert-Rein-Straße 1
14727 Premnitz
Tel. 03386 24-2531

For more information, please see: www.eon-energyfromwaste.com


 